COST TO COMPLETE

How to Calculate Cost to Complete for a Construction Project

Calculate remaining construction costs, outstanding commitments, sitework, contingency and potential funding gaps with a worked example.

By the FinNexios Editorial Team · · 9 min read · Leer en español

When a lender asks for Cost to Complete, it is asking how much additional money is needed, as of a defined reporting date, to finish the project to the required condition. This is different from the original project budget or the amount already spent.

1. What does cost to complete mean?

Start with each updated budget line and the actual work performed, allowing for approved scope changes. Estimate the remaining funds needed for construction, sitework, final inspections, professional services and contingencies.

Distinguish work still to be performed, unpaid invoices for completed work and contingency for future work. All may affect liquidity, but combining them without labels can confuse a lender.

2. A practical calculation method

  1. Set the report's as-of date.
  2. List unfinished units or components and their physical progress.
  3. Collect updated contractor estimates and certifications.
  4. Include sitework, utility connections and final common-area obligations.
  5. Add indirect completion costs, inspections and permits.
  6. Calculate appropriate contingency and compare with funds actually available.

The NCUA's lending guidance emphasizes evaluating whether the remaining budget is sufficient to finish construction.

3. Example: eight homes and remaining sitework

Assume eight homes require an additional $25,000 each. All figures below are hypothetical.

Remaining workAmount
8 homes × $25,000$200,000
Remaining sitework$80,000
Final permits and inspections$15,000
Illustrative contingency (10% of $280,000)$28,000
Estimated Cost to Complete$323,000

The contingency is calculated on homes and sitework here, not as a mandatory standard. If committed and available funding for the work is $275,000, the project has an illustrative $48,000 funding gap, before other restrictions or obligations are considered.

4. Compare remaining costs with sales carefully

If the eight homes are expected to sell for $1,760,000, that does not make $1,760,000 minus $323,000 the project profit. Prior land costs, completed construction, debt and other expenses still count. Evaluate net sales receipts, closing dates, loan releases and available cash.

5. Presenting the report to a lender

Include an as-of date, percentage complete by component, contracts, current estimates, approved change orders, out-of-scope work and available committed funds. A remaining construction and disbursement schedule shows whether funds arrive before payments fall due.

Related resources: construction draw schedules and hard vs. soft costs.

6. Review remaining costs with FinNexios

FinNexios helps update real estate development cost items, timelines and funding requirements. Reconcile model figures with actual construction documentation; a model does not replace professional inspection or certification.

Frequently asked questions

Does cost to complete include overdue invoices?

A complete funding review should show unpaid obligations, but distinguish them from physical work yet to be performed.

Can a sold home still have outstanding costs?

Depending on the agreement, punch-list, warranty or other obligations may remain after sale.

Should future loan interest be included?

Present future financing expenses as required by the report's scope and avoid double counting them in construction costs.

FROM IDEA TO FINANCIAL MODEL

Test financial feasibility before committing

Organize project costs, cash flow and scenarios using the currently available features.

Start with FinNexios ↗

Educational guide with hypothetical examples. Not a financing offer, legal advice or financial advice. Confirm terms and figures with qualified professionals.