How to Calculate Loan-to-Cost (LTC) for a Construction Loan
Learn the loan-to-cost (LTC) formula, a construction financing example, required equity and the difference between LTC and loan-to-value.
Loan-to-Cost (LTC) measures the size of a loan relative to the total costs recognized by the lender for a real estate development or renovation. It helps describe how much of the eligible project investment will be financed with debt.
1. The LTC formula
LTC = loan amount ÷ eligible total project cost × 100. The word eligible matters: a lender may exclude certain expenses, set category limits or use a different cost basis. Confirm the definition in the term sheet.
2. Example: a $3 million project budget
Suppose a hypothetical project has $3,000,000 of eligible costs and the lender proposes a $2,100,000 loan.
| Item | Amount |
|---|---|
| Eligible project costs | $3,000,000 |
| Proposed loan | $2,100,000 |
| Loan-to-Cost | 70% |
| Remaining capital sources | $900,000 |
LTC equals 70%. The remaining $900,000 would need to come from sponsor equity or other acceptable funding. This calculation does not promise loan approval or determine precisely when the equity must be contributed.
3. LTC versus Loan-to-Value (LTV)
Loan-to-Value compares the loan with an accepted property valuation, while LTC compares it with project costs. If this $2.1 million loan were measured against an approved value of $2.8 million, LTV would be 75%, even though LTC remains 70%.
Lenders may apply LTC, LTV, borrower liquidity, collateral and repayment criteria simultaneously. Meeting one ratio is not sufficient for credit approval.
4. What happens when costs rise?
Suppose eligible project costs increase to $3,300,000 but the loan commitment stays at $2,100,000. The arithmetic LTC falls to roughly 63.6% and other capital required rises to $1,200,000. The actual ratio may differ if the lender changes its eligible cost basis.
This example exposes the funding risk: additional construction costs may not automatically generate more available borrowing. Your cash flow needs to identify when and how the sponsor will cover the shortfall.
5. Use LTC with, not instead of, a cash-flow model
LTC describes leverage, not loan draw timing. Also review the construction loan draw schedule and sources and uses statement.
FinNexios helps organize real estate costs, debt and project funding assumptions for scenario analysis. Ensure the model aligns with the financing institution's definitions.
Frequently asked questions
Does 80% LTC mean the bank pays every invoice except 20%?
No. Eligible costs, equity contribution timing, reserves, draw rules and excluded expenses may create additional liquidity needs.
Is a higher LTC always better?
Not necessarily. It can reduce upfront sponsor equity but also increase leverage, repayment commitments and risk.
Is LTC a measure of profitability?
No. It measures financing relative to project costs, not expected returns.
Your project deserves a financial forecast
Model costs, revenue, cash flow and financing using available platform features.
Get started with FinNexios ↗Educational content with hypothetical examples. Not financial or legal advice or a financing offer. Verify terms and figures with qualified professionals.